Water, Power and Septic for an Off-Grid or Island Home: Designing the Systems Before the House

Oct 20
10 min read
Gulf Island construction site

On a serviced lot in Saanich the water, power and sewer are a line item. On a Gulf Island lot, or a lot at the end of a logging road, they are the first design decision, and they come in an order that does not bend: water, then septic, then power, then the house. Get the order right and the systems disappear into the building. Get it wrong and the house ends up where the septic field should have been, with a well that turns salty in August. This is what each system requires in British Columbia in late 2026, what it costs, and how we decide it before the drawings start.


Water: well, rain, or both


Most island houses draw from a drilled well, and a coastal well has one enemy: the sea. The Province's 2023 sea water intrusion advisory for the Southern Gulf Islands sets the operating limits a well owner should hold to: chloride below 150 milligrams per litre, electrical conductivity below 1,000 microsiemens per centimetre and total dissolved solids below 700 milligrams per litre. It recommends not drilling within 50 metres of the coast and not hydrofracturing within 100 metres, keeping the pumping drawdown above sea level, fitting a flow-limiting valve, and testing chloride, conductivity and solids every year in the dry season. The Water Sustainability Act prohibits operating a well so as to cause saline intrusion, and an owner who salts the aquifer can be liable to the neighbours who share it. A domestic well needs no licence, but any well drilled or altered since February 29, 2016 must be reported to the provincial registry within 90 days, which the driller does. We ask for the pumping test and the chemistry before we believe a well, and on a lot near the water we assume the well will be set back from the shore even when the house is not.

Rainwater is the other source, and on the dry islands it is often the primary one. The Province's guidance for potable rainwater, now part of the Drinking Water Officers' Guide, says rainwater used for drinking must be disinfected, recommends filtration plus disinfection, sets a minimum four-log reduction of viruses and of Giardia and Cryptosporidium, treated turbidity under one nephelometric unit, no detectable E. coli, and storage kept below 25 degrees to keep Legionella out. It references the CSA B805 rainwater harvesting standard. A system serving one single-family house is exempt from the guideline, which means the owner is trusted to meet it rather than excused from it; a system serving a guest house as well may not be. The CRD, for its part, will not accept a rainwater supply for a building permit without a mechanical engineering design. Island Health's recent precedent is the Gabriola community health centre, whose potable rainwater system received its operating permit in February 2026 on the principle that drinking-water rainwater must meet a higher treatment standard than irrigation water.

The islands then set the tank. Mayne requires 13,640 litres of cistern capacity for each additional dwelling on its listed lots. Galiano's new groundwater bylaw, given its adoption report in September 2025, requires at least 18,000 litres for any new dwelling outside a water service area, up from 16,000, and does not require the stored water to be potable or plumbed to the house outside its water management areas. Saturna's current bylaw requires 21,820 litres, with an amendment to 18,000 awaiting adoption. Those are minimums written for a drought summer, and 2026 was one: Vancouver Island's snowpack was zero per cent of normal on June 1, and the Island reached drought level 3 over the summer. For a large house with a garden, we size the storage from the roof area, the dry-season demand and the months between rains, not from the bylaw floor.

Fire water is a separate question with a plain answer. We found no CRD requirement for on-site fire water storage or residential sprinklers in a single-family house on the islands; what the CRD requires is a driveway strong, wide and graded enough for a fire truck within 30 metres of the house. A fire reserve held at the bottom of the cistern, with a fire department connection at the road, is a design choice rather than a code requirement, and one we raise with every island client.


Power: the grid, the sun, or both


Which grid you are on decides half the design. BC Hydro serves Salt Spring, Pender, Saturna, Mayne and Galiano, and is reinforcing the islands with an 11-kilometre submarine cable from Welbury Bay to Port Washington, laid in the summer of 2026 and scheduled to be energized in September. Sidney Island's strata lots are off-grid, with propane delivered to the island; a current listing there describes a 65-kilowatt inverter system, lithium batteries, 52 panels and several generators, which is the scale of a large off-grid house done properly. Piers Island, five minutes from Swartz Bay, has North Saanich water and BC Hydro power, and in September 2025 was funded for fibre to all 129 households. The smaller private islands are mostly off-grid, and their status is a question for the listing, not an assumption.

If the lot is on the grid, the economics of solar changed on July 1, 2026. BC Hydro's net metering rate closed to new customers and a self-generation service replaced it: exports are paid at 10 cents per kilowatt-hour and netted against consumption on each bill, against a retail price of 10.73 cents for the first 1,350 kilowatt-hours of a two-month bill and 13.62 above. Customers already on net metering keep it for ten years from their start date. BC Hydro's rebates remain, at $1,000 per kilowatt of solar to $5,000 and $500 per kilowatt-hour of battery to $1,500, or $5,000 for a battery enrolled in its peak-saver program, with the installer required to be a Home Performance Contractor Network member from June 1, 2026. The rebates do not apply to an off-grid house; the property must be connected. The practical consequence is that a grid-tied island house now sizes its array to its own consumption and uses a battery to carry the evening, rather than building a bigger roof to sell to the utility.

If the lot is off the grid, the design starts with the load, not the panels. A heat pump, an induction range, a well pump, an electric water heater and an electric vehicle charger add up to a house that a small system cannot run in January, when a south-coast array produces a fraction of what it does in July. Canadian vendors in 2025 put a full-time off-grid home with a 4 to 7 kilowatt array and 15 to 25 kilowatt-hours of battery at $20,000 to $35,000, and a high-demand system with 10 kilowatts or more and 30 to 50 kilowatt-hours at $50,000 to $75,000 and up. BC Hydro's own grid-tied benchmarks, cited in June 2026, are $2,000 to $3,000 per kilowatt installed and $18,000 to $25,000 for a residential lithium battery. A large custom home with electric heat on a remote site sits above all of those once the generator, the propane, the trenching and the barge are counted, and it is the generator that makes the house work: a propane or diesel set, sized to carry the winter deficit, with propane also feeding the range and the backup for hot water.

The Zero Carbon Step Code complicates propane. The CRD has required EL-3 for every new building in its electoral areas since January 1, 2024, which in its own description means the primary heating and water heating systems are electric in most cases, while a propane range and propane or wood secondary heating are allowed. The staff report that recommended the bylaw also recommended exempting areas without hydro power. That exemption does not appear in the consolidated bylaw text we read, so an off-grid lot in the CRD's electoral areas should confirm with CRD Building Inspection, early, how an energy advisor will model a house whose only electricity is its own. Province-wide, EL-1 has applied to most new buildings since March 10, 2025, and the performance path lets an energy advisor account for combustion appliances in the model.


Heating, cooling and the stove


Heat pumps are the default under the Step Code and the right answer on the coast, where the air rarely tests their floor; BC Hydro's guidance puts typical units at full efficiency to about minus 8 degrees and cold-climate units to minus 30, at 250 to 400 per cent efficiency. Off-grid, the question is not the cold but the battery, because the heat pump draws hardest on the dark January evening when the array has produced nothing since three o'clock. That is the case the generator is sized for, and it is why many off-grid houses keep a certified wood stove as the second heat source. The 2024 building code also requires, for the first time, that a new house be capable of holding one living space at 26 degrees or less in summer, by passive design, a heat pump in cooling mode, or both.

A wood stove is regulated at the point of sale: only appliances certified to the CSA or US EPA emission standards may be sold in BC, burning seasoned untreated wood, and outdoor wood boilers need a 40 metre setback from the property line. There is no island bylaw against a stove; Salt Spring's approach is incentive, with provincially funded rebates of $1,500 toward a heat pump, $600 toward a certified stove and $300 for decommissioning an old one on quotes dated between January 2026 and January 2027. A WETT inspection of the installation is a condition insurers commonly set rather than a legal requirement, and we treat it as a requirement.


Septic: the field sizes the house


Island Health governs the septic system under the provincial Sewerage System Regulation, which covers any system under 22,700 litres a day. Only an authorized person, a registered onsite wastewater practitioner or a professional engineer, may design and install it; the practitioner files the design with Island Health before construction and a letter of certification within 30 days of completion, and the owner must maintain the system to the filed maintenance plan. A Type 1 system is a septic tank and dispersal field. Type 2 treats the effluent to under 45 milligrams per litre of suspended solids and biochemical oxygen demand; Type 3 to under 10, with a fecal coliform limit, and only an engineer may design it. Type 2 and 3 exist for the lots where the soil, the slope or the setbacks will not accept a Type 1 field, which on a small waterfront lot is common.

The setbacks are what draw the site plan. The standard practice manual places a dispersal field 30 metres from a well, 30 metres from a lake or stream, 15 metres from the sea, 7.5 metres from any point where effluent could break out downslope, 3 metres from a property line and 15 metres from a below-ground cistern, with the tank itself allowed closer. Draw those circles on a half-acre waterfront lot and the field often has one possible location, which fixes the house, the driveway and the well. The bedroom count sets the design flow, so the house plan feeds back into the field size; a four-bedroom house is designed around 1,600 litres a day in the usual practice. The practitioner's site assessment, with test pits, therefore belongs before the architect's first sketch, not after.

Costs in BC, as one treatment manufacturer published them in August 2026: a Type 1 installation at $19,000 to $31,000, or $22,000 to $36,000 with assessment and design; a Type 2 or 3 at $42,000 to $80,000 and up, or $45,000 to $85,000 all in; a site assessment at $350 to $1,250; design at $2,500 to $3,500; pump-outs at $400 to $700 every two to five years. Where the CRD regulates maintenance directly, as it has in North Saanich since January 1, 2025, a Type 1 tank must be pumped at least every five years and a Type 2 or 3 serviced by an authorized person annually. That bylaw does not reach the islands, but the schedule is the right one, and it goes into the owner's manual we hand over.


Connectivity


A remote site needs a connection before it needs a crew, because the daily log, the photographs and the schedule you follow from wherever you are depend on it. Starlink's residential pricing in Canada was cut in January 2026 to $70 a month for 100 megabits, $110 for 200 and $140 for its top tier, with hardware around $399 and free kits in some areas, which makes it the default on any lot without fibre. The Province's target is for every remaining underserved household to be connected by 2027 under its joint program with Ottawa, and islands such as Piers are already funded. Cell coverage on the islands varies by bay and by carrier, and we test it on the lot rather than trust the map.


The order of decisions


Water first, because a lot that cannot produce water cannot carry a house, and because the well's location and its chemistry decide whether a cistern is a supplement or the supply. Septic second, because the field's setbacks from the well, the shore and the lines decide where the house can stand. Power third, because the load the house will carry decides whether the roof is a solar array, the yard holds a generator, and the range runs on propane. The house last, drawn around the three. We run those decisions in pre-construction with the well driller, the wastewater practitioner, the solar designer and the energy advisor at the table, price the systems with the house rather than as allowances, and put the maintenance schedule for every one of them, filters, lamps, pump-outs and batteries, in the manual you receive at handover.


Questions we're asked


Can we drink rainwater? Yes, with treatment: filtration and disinfection to the Province's guidance, which the CRD will want to see as a mechanical engineering design. A single house is exempt from the formal guideline, which is a reason to meet it, not to skip it.

How big does the cistern need to be? At least the island's minimum, which is 13,640 litres on Mayne for an additional dwelling, 18,000 on Galiano under its new bylaw and 21,820 on Saturna under the current one. For a large house on a dry island we size from the roof, the summer demand and the gap between rains, which usually means more.

Does BC Hydro pay for the power my solar exports? Since July 1, 2026, new customers are paid 10 cents per kilowatt-hour, netted on each bill, under the self-generation service that replaced net metering. Rebates of up to $5,000 for panels and $5,000 for a battery apply to grid-connected houses only.

What does an off-grid power system cost? Vendors in 2025 quoted $20,000 to $35,000 for a modest full-time home and $50,000 to $75,000 and up for a high-demand one, before the generator, propane and remote logistics. A large custom home with electric heat is above that range, and we price it from the load.

Can we heat with propane on an off-grid lot? Under the CRD's EL-3 rule the primary heat is electric in most cases, with propane allowed for the range and as a secondary source. Whether an off-grid house can be modelled differently is a question we put to CRD Building Inspection before the design is fixed.

What does a septic system cost? In 2026, roughly $22,000 to $36,000 all in for a conventional system and $45,000 to $85,000 and up for a treatment system, which is what a small or waterfront lot usually needs.


Start a conversation


Tell us about the lot, whether it has power at the road, and whether anyone has ever tested the well. We'll tell you what the house can have, and in what order to find out.