How Long It Really Takes to Build a Custom Home in Greater Victoria: Permit Targets by Municipality and a Month-by-Month Schedule

Oct 22
8 min read
Custom home in Victoria, bc


The design clock: three to six months


Design starts with the lot and ends with a permit set, and it takes longer than owners expect because the permit set is not a sketch. A house here needs architectural drawings, a structural engineer's design for the whole building under the 2024 code's seismic rules, a site survey, an energy advisor's pre-construction compliance report to Step 3 of the Energy Step Code, and in most of the region an electric heating design under the Zero Carbon Step Code. Builders who publish figures put design at two to four months in Greater Victoria and pre-construction at four to six. Our own pre-construction phase runs the design, the engineering, the selections and the price together, because every selection decided before the permit is a week not lost during the build; a house whose windows, cabinets and tile are chosen in month three does not wait for them in month nine.


The approvals clock: by municipality


Victoria screens a single-family application for completeness, accepts it, charges $100, and states in its October 2026 checklist that once payment is received the targeted review time is seven business days; any development permit must be issued before the building permit is accepted, and the City's fee holiday sets building and plumbing permit fees to zero for complete applications received before January 29, 2027. Saanich publishes no review target for a new house. It moved to fully digital applications in April 2025, runs a pre-application process with BC Hydro among the reviewers, handled 33 pre-applications in 2025, and requires an archaeological response before a permit issues; its permits last two years with one extension of up to a year. Oak Bay asks applicants to allow several weeks, and in the Uplands the design must first go to the advisory design panel, which meets the first Tuesday of each month with submissions two weeks before, and then to Council. Sidney's homeowner guide puts processing at two to three weeks, reviewed in the order received, and now requires a construction fire safety plan with most permits. Central Saanich's agricultural properties page puts an initial review at four to six weeks. North Saanich quotes about three weeks. Langford runs an expedited stream for one- and two-family houses that its own checklist calls two-day permits, available only when every drawing, schedule, Step Code document and departmental approval is already in the package. The CRD, for the islands and Juan de Fuca, targets four weeks with a $300 application fee.

A variance is the approval that moves the calendar most. In Victoria a development variance permit runs through a 30-day neighbourhood comment period, a sign on the site at least ten days before Council and a Council decision; Sidney puts a variance at six weeks to two months and a development permit at six to nine weeks; a local builder's published estimate for a variance is ten to sixteen weeks. A house designed inside the zoning skips all of it, which is the single largest schedule decision an owner makes and is made at the first sketch.

The utility has its own clock. BC Hydro's express stream covers a house within 30 metres of its pole or underground infrastructure with a meter on the outside wall, reviews the documentation within two business days, and since July 5, 2025 applies a contribution allowance of $2,782 per dwelling that cut a simple connection fee from more than $800 to as little as $64; anything larger or further is a design project with a longer path. And the Building Code has a date in it: the 2024 code's seismic provisions apply to every application made on or after March 10, 2025, with a grace period for applications already in the queue that the Province's bulletin ends on March 8, 2027, so a project permitted on an older application should read that bulletin before it waits into 2027.


The construction clock: month by month


For a 3,000 to 5,000 square foot house on a serviced lot, this is the shape of the year, with the inspections Saanich, Langford and North Saanich require written in.

Months one and two are the ground: tree protection and erosion control, excavation, footings and foundation walls, perimeter drains and dampproofing, the under-slab radon rough-in the 2024 code requires in every new house, under-slab plumbing, slab insulation and the slab, with the inspector called at excavation and footings, forms, radon, under-slab plumbing, insulation, drains and the service laterals. Rock and water make this the most variable stretch; the article on rock, slope and trees in this series explains why.

Months three to five are the frame: floors, walls, roof and sheathing, the surveyor's certificate of the foundation's position and height before the framing inspection, then the windows and doors, which were ordered in month zero because builders here quote twelve to twenty weeks for custom and triple-glazed units. The house is dried in, and the aim is to be dried in before the rains.

Months five to seven are the rough-ins: plumbing, electrical, the heat pump and ventilation, the low-voltage conduit, the pre-cladding and rainscreen inspection, then insulation and the air barrier, where the energy advisor's mid-construction check happens, Langford requires its Step Code checklist, and Saanich recommends a blower-door test it does not require. The fire separations are inspected, and the drywall goes on.

Months seven to eleven are the finish: exterior cladding and roofing complete, drywall and paint, millwork, tile, flooring, fixtures and appliances, in the order the trades can work without waiting on each other, which is the project manager's craft. Builders who publish figures put interior finishing at three to four months on its own.

Months eleven to thirteen are the end: final inspections, the energy advisor's as-built report, the occupancy permit, the landscaping and the driveway, the handover and the warranty's start. Published local figures for the construction clock alone run from eight to fourteen months; our schedules for a house of this size on a serviced lot run eleven to fourteen, and they say so before the contract is signed.


The weather clock


Victoria's rain is seasonal enough to plan around: roughly three-fifths of the year's 600 millimetres falls between November and February, with November the wettest month and July, at about 10 millimetres, nearly dry. Foundations and framing go best from April to October; a house that is dried in by November carries its interior work through the wet months without losing a day to them. Excavation in January on a clay site is possible and slow. The regional market sets the other half of the weather: CMHC counted 202 single-detached starts in the Victoria area in the first nine months of 2026, down 4 per cent, with 9,353 units of all kinds under construction, which is a reasonable year for finding good trades and a poor one for finding them at a week's notice.


What adds months


Variances, as above. Archaeology, which Saanich requires an answer on before any permit and which, where a provincial heritage permit is needed, runs on the Province's clock. Trees, which need an arborist's report and management plan before the permit in Victoria, Saanich, Oak Bay and most of the region, and whose removal is best kept outside the nesting season of late March to mid-August. Rock, which needs a blasting permit with 48 hours' written notice to the neighbours in most municipalities and, in Oak Bay since 2026, a permit with a life of twenty to thirty business days and rock-breaking confined to four hours a day. Agricultural land, where a Commission application has a 60-business-day target the Commission met 29 per cent of the time in 2024–25. A BC Hydro design project where the express criteria are not met. Long-lead materials: windows at twelve to twenty weeks, cabinetry and specialty finishes at eight to twelve, and since September 8, 2026 the counter-tariffs on American steel, aluminum, appliances and heat pumps that have lengthened some supply chains. Incomplete applications, which every municipality returns to the back of the queue, and which Langford's two-day stream simply refuses. And permit expiry: Saanich gives two years and one extension, Langford six months to start and twenty-four to finish, the CRD four years, so a long design phase after the permit is a real risk rather than a theoretical one.

Two kinds of lot carry a clock of their own. A teardown adds a season before the build: a hazardous materials survey measured in days, abatement in weeks, a demolition permit on the municipality's own timeline, and demolition in days or deconstruction in several weeks, timed around the nesting season and, in Victoria, the deconstruction bylaw. Agricultural and acreage land adds the Commission's: a notice of intent for fill runs on a 60-day clock, and anything that needs an application runs on targets the Commission met for a minority of files last year. Both are covered in their own articles in this series, and both are reasons to start the approvals before the design is finished rather than after.


How we keep it on time


The schedule is written in pre-construction, with the design and the price, and it is built from the municipality's own review target, the inspection sequence, the utility's criteria and the long-lead orders outward. The application goes in complete, once. The windows, the doors, the cabinetry and anything with a quoted lead time are ordered before the foundation is poured. The house is designed inside the zoning so no variance stands between the drawings and the permit, and sited so the trees and the rock are known before the excavator arrives. Then the project manager and the site manager run the year, inspection by inspection, and the daily log, the photographs and the schedule are in one place you can open from anywhere, so the question of how long is answered every day rather than at the end.


Questions we're asked


How long does a custom home take from start to finish? Fifteen to twenty-four months from the first meeting to the keys for a 3,000 to 5,000 square foot house on a serviced lot without variances: three to six months of design and pre-construction, a permit of weeks to a few months depending on the municipality, and eleven to fourteen months of construction.

How long does the building permit take? Victoria targets seven business days of review once a complete application is paid for; Sidney quotes two to three weeks; North Saanich about three; Central Saanich four to six for an initial review; Oak Bay several weeks; the CRD four weeks. Saanich publishes no target. A variance adds two to four months anywhere.

Can we build through the winter? Yes, if the house is dried in by November. Foundations and framing are best started between April and October; interior work runs through the wet months without loss.

What is the most common delay? An application that is not complete, followed by a variance, a tree, or a window order placed after the permit instead of before it.

When should the windows be ordered? Before the foundation is poured. Local builders quote twelve to twenty weeks for custom and triple-glazed units in 2026.

How long is a building permit valid? Two years in Saanich with one extension of up to a year; in Langford work must start within six months and finish within twenty-four; the CRD allows four years. Check your municipality before a long pause.


Start a conversation


Tell us where the lot is and when you'd like to be living there. We'll give you a schedule built from the municipality's own numbers, and the date we would start to meet it.



It's time for a home

built around you. 

Uncompromising Craftsmanship Since 1998

bottom of page