BC Step Code and Zero Carbon Step Code, Explained for Homeowners Building in Greater Victoria (2026)

Oct 20
8 min read
blower fan in construction site

Two energy codes apply to every new house in British Columbia, and most people building one have heard of neither until the energy advisor's invoice arrives. The BC Energy Step Code sets how efficient the building has to be. The Zero Carbon Step Code sets how much carbon its heating, hot water and appliances may emit. Together they decide the insulation, the windows, the airtightness, the heating system and, in most of Greater Victoria, whether a gas line to the house is worth running at all. They are not the same everywhere: a house in Saanich is held to a different standard than one in Sidney, and Langford's standard changes on December 1, 2026.

This is what the two codes require, what they mean on site, what they add to the cost and what they return, as the rules stood in October 2026.


Two codes, one house


The Energy Step Code is a ladder. Step 1 is the base building code; Step 5 is a net-zero-energy-ready house. Since May 1, 2023, every new house in BC must meet at least Step 3. The Province's stated path is to require net-zero-energy-ready construction by 2032. The Zero Carbon Step Code is a second ladder, for emissions. Emission Level 1 only requires that emissions be measured; Levels 2, 3 and 4 progressively remove fossil-fuel equipment. Since March 10, 2025, every new building in BC must meet at least Level 1, and the Province's path is to require zero-carbon new construction by 2030. Municipalities may require higher steps and levels than the provincial minimum, and most in this region do.


What the Steps mean on a house


For a Part 9 house in this climate zone, the Steps are defined by three measured quantities: airtightness, tested with a blower door and expressed as air changes per hour at 50 pascals; the energy the house needs for heating, per square metre per year; and the mechanical energy use intensity, which includes heating, cooling, hot water and ventilation.

Step 3 requires 2.5 air changes per hour, a heating demand of 30 kilowatt-hours per square metre and a mechanical intensity of 50. Step 4 tightens those to 1.5, 20 and 40. Step 5 requires 1.0 air changes, 15 and 25. For a sense of scale, a well-built 2018-code house tested at around 3.0 air changes; Step 3 is roughly 20 per cent better than that code, and Step 5 is a house that needs a fraction of the heating.

On site, the Steps show up as four things: thicker or better-detailed insulation and higher-performance windows, which the energy model decides; an air barrier that is designed, drawn and sealed rather than assumed; a heat-recovery ventilator, because a tight house needs controlled fresh air; and testing. An energy advisor models the house before the permit, the house is blower-door tested at the vapour-barrier stage so leaks can still be found and fixed, and an as-built report and an EnerGuide label are produced before occupancy. Every municipality in Greater Victoria requires the pre-construction compliance report with the permit application.


What the Emission Levels mean


Emission Level 1 requires a greenhouse-gas calculation and nothing more. Level 2 requires electric space heating or electric hot water. Level 3 requires both. Level 4 requires full electrification on the prescriptive path, with performance-path limits of 1.5 kilograms of carbon dioxide per square metre per year and 500 kilograms per year for a house.

In practice, Level 4 means a heat pump for space heating and a heat pump or electric water heater for hot water, with no gas furnace, boiler or gas water heater. The Province's guidance is that gas cooktops and barbecues fall outside the Part 9 compliance calculation, and Victoria's and Oak Bay's guidance allows a redundant or backup heating appliance if it has dedicated controls and is not sized to carry the load. A gas fireplace may or may not fit, depending on the model; Saanich models any fireplace at a fixed annual consumption. If a gas appliance matters to you, raise it in design, not at rough-in.


What your municipality requires


Every municipality in the region requires Step 3 as the energy minimum for a new house. The emission level is where they differ.

Victoria requires Level 4 for all Part 9 permits since November 1, 2023. Saanich requires Step 3 (May 1, 2023) and Level 4 (November 1, 2023), and applies both to garden suites. Oak Bay requires Step 3 and Level 4, with greenhouse-gas reporting on all new construction since September 1, 2024. Central Saanich requires Step 3 and Level 4 for all new residential. Esquimalt has required Level 4 for Part 9 permits since January 1, 2024. View Royal requires Step 3 and Level 4. Colwood adopted Step 3 and Level 4 for Part 9 permits from March 4, 2024.

Langford is in transition: Level 1 from March 10, 2025, Level 2 from July 1, 2026, and Level 4 for permits from December 1, 2026, under its building bylaw as consolidated in June 2026; Langford also now requires a land surveyor's certificate before the framing inspection. Sidney requires Step 3 and only the provincial Level 1, so a gas furnace remains code-legal in Sidney as of this writing. North Saanich requires Step 3 under its building bylaw and has not adopted a municipal emission level, so the provincial Level 1 applies. Highlands has required Step 5 for a new single-family house since January 2, 2023, or Step 3 for houses up to 420 square metres and Step 4 above that when paired with a low-carbon heating system. Metchosin, Sooke and the CRD's electoral areas have not published a municipal level on their own pages; the CRD's building permit checklist for the Gulf Islands and Juan de Fuca lists Step 3 with Level 3.

The level is set by where the lot is, and it is one of the first things we confirm when a client brings us a property.


What it adds to the cost


The incremental cost of the Steps has been studied repeatedly, and the numbers are smaller than the reputation. A 2024 costing prepared for the City of Richmond put a single-family house at Step 3 at 1.1 per cent above the baseline, Step 4 at 1.4 per cent and Step 5 at 2.7 per cent. Nanaimo's 2023 staff report, citing provincial costing, put Level 4 electrification at up to 0.6 per cent for a single-family house and the top energy step at 1 to 6.6 per cent, with utility costs ranging from a 12 per cent decrease to a 7 per cent increase depending on the design. Victoria's own 2023 analysis found the Level 4 capital premium to be one per cent or less for every house type in its climate zone.

Those percentages hide where the money actually goes: the energy advisor, the blower-door tests, a heat-recovery ventilator, better windows and a heat pump instead of a furnace. On a custom home, most of that was going into the house anyway. The real cost of the code is in the design time it demands, which is why the energy model belongs in the first set of drawings rather than the permit set.


What it returns


The return shows up on the hydro bill and in the rooms. Saanich's 2023 Make the Switch study followed 24 homes that replaced gas with heat pumps, half of them on southern Vancouver Island, and found total energy costs down about 10 per cent and emissions down 73 per cent, with 97 per cent of households rating the heat pump better or much better than what it replaced. BC Hydro has put the utility saving from heat-pump space and water heating at as much as 25 per cent. A 2023 Canadian Climate Institute analysis found heat pumps cheaper over their life than gas in five Canadian cities including Vancouver.

A tight, well-insulated house is also a quieter and more even one: fewer drafts, no cold wall by the window in January, no 30-degree bedroom in August. The 2024 building code now requires that at least one living space can be kept at or below 26 degrees, so cooling is part of every new house here, and a heat pump provides it as a matter of course. The 2024 code also brought in a radon rough-in across the province and full-height foundation insulation, both of which are now part of the baseline rather than extras.


What's coming


The Province has set the end points, zero-carbon new construction by 2030 and net-zero-energy-ready by 2032, and has not published fixed dates for the steps in between. The 2017 schedule that anticipated Step 4 by 2027 remains the common expectation in the industry, and several municipalities, Langford most recently, are moving ahead of the Province on emissions. Because the code applies as of the permit application date, a house designed in 2026 and permitted in 2027 may face a different requirement; we design to the standard the house will be permitted under, not the one in force when the sketch was drawn.


Rebates, as of October 2026


The rebates that once offset Step Code costs have largely closed. The CleanBC Better Homes New Construction Program, which paid builders up to $14,000 for a Step 5 house and up to $4,000 for a heat pump, is closed. The federal Canada Greener Homes Grant closed to new documentation at the end of 2025, and the Greener Homes Loan is no longer approving applications; neither targeted new construction. FortisBC's New Home Program has offered rebates for homes built to Step 4 and Step 5 in its gas service areas; confirm its current terms before counting on it. The one new federal measure is the first-time home buyers' GST rebate, in force since March 2026, which returns the full GST on a new home up to $1,000,000, phasing out at $1,500,000, including owner-built homes under parallel rules. Where a program applies to your house we will point you to it; the budget should not depend on one.


How we build to it


Every house we build meets Step 3, because every municipality requires it, and we build to Level 4 wherever the municipality does and wherever a client asks for it elsewhere. The energy advisor is part of the design team from the first drawings, so the model shapes the house rather than auditing it afterward; the air barrier is drawn before it is built; and the blower-door test at the vapour-barrier stage is scheduled, not hoped for. If you want a Step 4 or Step 5 house, say so at the start, because those are design decisions about form, glazing and orientation, not upgrades to add later.


Questions we're asked


Do I have to install a heat pump? In Victoria, Saanich, Oak Bay, Central Saanich, Esquimalt, View Royal and Colwood, and in Langford from December 1, 2026, Level 4 effectively requires electric space and water heating, which in practice means a heat pump. In Sidney and North Saanich the provincial Level 1 applies and the choice is yours.

Can I have a gas cooktop or a gas fireplace? Cooktops and barbecues sit outside the Part 9 compliance calculation. A gas fireplace depends on the model and the municipality's modelling rules. Decide in design.

What is a blower-door test? A fan in the doorway depressurizes the house and measures how much air leaks in. Step 3 allows 2.5 air changes per hour at test pressure; Step 5 allows 1.0. The mid-construction test is the one that matters, because leaks found then can still be sealed.

How much does Step Code add to a custom home? Published costings put Step 3 at about 1 per cent, Step 5 at about 3 per cent and Level 4 at 1 per cent or less, before energy savings.

Is Step 5 worth it? For a house you intend to stay in, usually, but it has to be designed as one: compact form, right-sized glazing, orientation to the sun. Added to a finished design it is expensive; built into the first sketch it is not.

Which rules apply if the code changes during my project? The rules in force when the building permit application is accepted. We design to the standard the house will be permitted under.


Start a conversation


Tell us where the lot is. We'll tell you which Step and which Level the house will be built to, and what that means for the design.